Applying for a Maximum Construction Capacity (MCC): What New Builders Need to Know

If you are preparing to start domestic building work in Victoria, one of the first things you need to understand is the Letter setting out your Maximum Construction Capacity (MCC).

From 1 July 2026, new financial and insurance requirements apply to builders undertaking domestic building work in Victoria. These reforms introduced the Minimum Financial Requirements (MFRs), Home Warranty and Maximum Construction Capacity (MCC).

Financial requirements determining your MCC

The BPC needs to see that you hold sufficient assets to pay your debts when they fall due. Based on this, the BPC will calculate your MCC – which determines the maximum total value of domestic building work you can undertake at any point in time.

The BPC calculates your MCC using your Adjusted Net Tangible Assets (ANTA), which is your assets (minus any items which BPC does not count) minus liabilities. The formula is:

  • For an MCC up to $20 million: ANTA divided by 5%
  • For an MCC above $20 million: ANTA minus $400,000, divided by 3%

In calculating your ANTA, the BPC will usually include assets such as cash, amounts owed to you, inventory, property, vehicles, plant and equipment, listed shares and tools of trade. It will not count items such as cryptocurrency, unlisted shares, personal furniture, recreational vehicles or superannuation you cannot access.

Trust assets and guarantees may also be considered if you provide the right supporting documentation.

If the domestic building company is part of a group of companies, you can choose whether your MCC is assessed at the individual entity level or across the group. The BPC does not require annual financial reports from every builder, but it can request such information at any time.

If your MCC reaches $2 million or more, you will need to maintain quarterly internal management accounts and provide them to the BPC, verified by a qualified accountant, within 14 days of any request.

If you suspect your workload is likely to grow beyond your approved MCC, it’s important to apply for an increase before you reach the limit. The BPC may direct you to reduce your workload, inject capital or submit a Financial Recovery Plan in these circumstances. Failure to comply and exceeding your MCC can lead to disciplinary action, including the immediate suspension of your registration.

Tip: Speak to an accountant before you apply to become a registered domestic builder. A clear picture of your ANTA from the outset will help you secure the right MCC.

Home Warranty

Home Warranty replaces the former Domestic Building Insurance model. The key differences are that the maximum coverage available under Home Warranty has increased to $400,000 and that your customers can now access cover while you are still actively trading, not only if you become insolvent, disappear, die or fail to comply with a court or tribunal order. Home Warranty may respond to claims for incomplete, non-compliant or defective work.

From 1 July 2026, Home Warranty applies to domestic building work under an insurable domestic building contracts entered into from 1 July 2026 over $20,000, except for work relating to a class 2 building with a rise of more than three storeys.

Cover automatically starts on either the date the applicable premium is paid by you, once you sign an insurable domestic building contract with the owner or start the domestic building work (whichever is the earlier).

You must apply for a Notice of Cover and pay the applicable premium to BPC within 10 business days of the earlier of signing the contract with the owner or commencing the work. Failure to do so, is a breach of the Building Act 1993 and may result in you facing disciplinary proceedings.

Home Warranty covers claims for assistance from owners up to a maximum of $400,000, with major defects covered for six years and all other defects covered for two years from completion of the work.

Rectification Orders

A Rectification Order is a formal written direction from the BPC under the Building Act 1993. Under the Order, BPC can require you to fix incomplete, non-compliant or defective work within a set timeframe.

Any builder, new or established, can receive a Rectification Order at any stage of a project, including during construction, during the defects liability period or after the work is completed.

A Rectification Order will set out:

  • What work is considered incomplete, non-compliant or defective
  • Require you to complete and/or rectify non-compliant or defective work at your cost
  • Specify the timeframe within which you must complete the required actions
  • Any other conditions which may be necessary to ensure the work is completed and/or rectified as required by BPC

If you receive a Rectification Order from BPC, you must complete the work specified within the required time frame, keep records and work with the BPC throughout the process. Subcontracting the work to a contractor will not absolve you from responsibility for complying with a Rectification Order.

Non-compliance can lead to fines, work stoppages, disciplinary action and reputational damage.

If you are planning to carry out domestic building work as an owner builder

If you are building or renovating your own home without being a registered building practitioner or architect, and such work requires a building permit, you will need to apply for a certificate of consent from BPC before undertaking any such work. In this case, the owner builder provisions under the Building Act 1993 will apply to you, and you will be responsible for any defective or non-compliant work in the same way as a registered building practitioner.

You become the Responsible Person for your build. This means you owe statutory warranties to the homeowner and any future purchaser, you must rectify defective, non-compliant or incomplete work, and you can be issued with a Rectification Order just like a registered building practitioner.

Before you start any work as a owner builder, make sure you:

  • Obtain your Certificate of Consent from BPC if the domestic building work requires a building permit
  • Confirm product and installation requirements early
  • Keep records from day one for any supplies or materials purchased or subcontracts entered into by you and all documents provided to, or issued by, the relevant building surveyor for the project (these should be kept for 10 years after completion of the work)

If you plan to sell the property within 6 ½ years of completion of the work, you will also need to obtain an inspection report for the work and apply for Home Warranty through the BPC, paying the applicable premium before you enter into a contract of sale for the property.

Your inspection report should cover defective or non-compliant work, any second-hand materials used in construction, including colour photographs of all such work. Failure to include such items in the inspection report means that you will be responsible for rectifying the defective or non-compliant item at your cost.

Note: Defects identified in your inspection report are generally excluded from Home Warranty cover.

Next steps

The legislative changes which took effect on 1 July 2026 raise the compliance bar for everyone doing domestic building work in Victoria. Understanding your financial obligations, insurance requirements and compliance responsibilities will put you in the best position from day one to ensure that you meet your legal obligations.

If you are unsure about anything, speak to your accountant, a registered building practitioner, a building surveyor, your local council or contact the BPC directly before you begin.

The Letter of Eligibility has been replaced by the Letter of Maximum Construction Capacity from 1 July 2026. The new process places greater emphasis on demonstrating your financial position, specifically your Adjusted Net Tangible Assets (ANTA), as your ANTA is directly linked to your approved maximum construction capacity (MCC) and must be maintained at this level to remain registered. Your MCC is the total amount of domestic building work which you can undertake at any point in time.

Your MCC is calculated based on your Adjusted Net Tangible Assets (ANTA). Generally, the stronger your financial position, the higher your MCC. Speaking to an accountant before you apply will help you understand your ANTA and apply for the right MCC from the start.

You must apply to BPC for an MCC increase before you reach your MCC limit, as soon as you first suspect there may be a risk that your volume of work could exceed your MCC. If you exceed your MCC limit without having come to an arrangement with us, you will be in breach of the minimum financial requirements (MFRs), which are a precondition to you remaining registered.

Not automatically. BPC can request you to provide financial and other information reasonably required to be able to assess your compliance with the MFRs at any time. However, the MFRs do not require full annual reports to be provided to BPC by every builder. If your MCC is $2 million or more, you will need to maintain quarterly internal management accounts and provide them to BPC, verified by a qualified accountant, within 14 days of request.

Home Warranty replaces the pre-1 July 2026 Domestic Building Insurance (DBI) model. Unlike DBI where the entitlement to claim was only activated if a builder died, disappeared, became insolvent or failed to comply with a court or tribunal order, Home Warranty allows your customers to access cover while you are still actively trading. A claim for assistance can be made for incomplete, non-compliant, or defective work.

A Rectification Order (RO) is a formal written direction from BPC requiring you to fix incomplete, non-compliant, or defective domestic building work undertaken by you within a set timeframe. Any builder, new or established, can receive a RO at any stage of a project. Complying fully with the RO and within the timeframe required is essential, as non-compliance may have financial, reputational and disciplinary implications for you.

Yes, if you are acting as an Owner Builder and carrying out domestic building work which requires a building permit and a certificate of consent. From 1 July 2026, Owner Builders who have carried out domestic building work under a certificate of consent, become the "Responsible Person" for their build and carry the same compliance obligations as a registered builder, including the potential to receive a Rectification Order requiring incomplete, defective or non-compliant work to be fixed at the Owner Builder’s cost.

Build your future.

Start the journey with BRIC today.

This publication is not intended to be taken as advice regarding any individual situation and should not be relied upon as such. The information contained herein is based on sources we believe reliable, but we make no representation or warranty as to its accuracy. BRIC shall have no obligation to update this publication and shall have no liability to you or any other party arising out of this publication or any matter contained herein. Any statements concerning actuarial, tax, accounting, or legal matters are based solely on our experience as insurance brokers and risk consultants and are not to be relied upon as actuarial, accounting, tax, or legal advice, for which you should consult your own professional advisors. Any modelling, analytics, or projections are subject to inherent uncertainty, and any analysis could be materially affected if any underlying assumptions, conditions, information, or factors are inaccurate or incomplete or should change.

Bovill Risk & Insurance Consultants Pty. Ltd. (BRIC); ABN 78 072 412 474 is a Corporate Authorised Representative of Honan Insurance Group Pty Ltd (AR 1308194), a part of the Marsh Group of companies.

This website contains general information, does not take into account your individual objectives, financial situation or needs and may not suit your personal circumstances. For full details of the terms, conditions and limitations of the covers and before making any decision about whether to acquire the product, refer to the specific policy wordings, product disclosure statements and/or target market determination (TMD) available from BRIC on request.

LCPA 26/3671